File #: 16-0204    Version: 1 Name: Downtown Waterline Project
Type: Contract Status: Passed
File created: 4/28/2016 In control: City Council
On agenda: 5/12/2016 Final action: 5/12/2016
Title: Discussion and action on Downtown Waterline Project
Sponsors: Engineering Department, Tim Begley
Attachments: 1. Downtown Proposed Waterlines Map, 2. Supplemental agreement CT Consultants, 3. Total Construction Cost Estimate.pdf

Title

Discussion and action on Downtown Waterline Project

Body

SUMMARY: As discussed in the February Council Meeting, the City has an estimated $375,000 funding available through SRF remaining after the extension to Genesis. City staff has reviewed the downtown area and located areas with deficient waterlines. These areas are shown on the attached map and generally described as East Fourth Street, Thurman Avenue (from East Fourth Street to East First Street), East First Street (from South Main Street to Thurman Avenue), Rector Avenue (from West Fifth Street to West Fourth Street), East Fifth Street (from North Main Street to Thurman Avenue), Stanley Street (from South Main Street to West Avenue) and Taylor Avenue (from North Main Street to Thurman Avenue). City staff has developed a construction estimate utilizing the contract prices which totals $335,000.

 

Staff recommends the approval of the attached supplemental agreement with CT Consultants at a total approved cost of $24,000 and approve preliminary change order 4 with Ironwood construction at $335,000. 

 

BUDGET ACCOUNT:

 

Recommended Action

NECESSARY COUNCIL ACTION: Approve supplemental agreement with CT Consultants at a cost of $24,000 and approve the preliminary change order number 4 with Ironwood Construction at a unit cost not to exceed $335,000 contingent on SRF’s approval.