Title
Ordinance amending the FY2017-18 budget for Water System Improvements
Body
SUMMARY:
The following bids were received on August 8, 2017 for improvements to the Meadow Park and Holiday water treatment plants:
• W & O Construction $1,291,600
• Roy Joe Angel Construction $1,364,000
• J. Cumby Construction $1,486,000
The low bid of W & O Construction was recommended by the consulting engineers for acceptance and awarded by City Council on August 23, 2017.
BUDGET ACCOUNT: 413-52130-920-003 $345,000
413-52130-920-004 $375,000
Budget amendment required.
Recommended Action
NECESSARY COUNCIL ACTION: Pass a budget amendment