File #: 17-0364    Version: 1 Name: Close Out Change Order for Safe Routes to Schools
Type: Contract Status: Passed
File created: 8/30/2017 In control: City Council
On agenda: 9/12/2017 Final action: 9/12/2017
Title: Approval of the Final Project Closeout Change Order #2 with Lori Neal & Associates on Safe Routes to Schools Project
Sponsors: Engineering Department, Tim Begley
Attachments: 1. Final Change Order SRTS

Title

Approval of the Final Project Closeout Change Order #2 with Lori Neal & Associates on Safe Routes to Schools Project

 

Body

SUMMARY: The final closeout change order for the Safe Routes to Schools project on Fourth Street and Myrtle Avenue is attached.

The change order has several items that are reduced in quantities but overall there was an increase of $33,581.80 in overrun items. The larger overrun items being curb & gutter, seeding, and topsoil.

 

BUDGET ACCOUNT:

 

Recommended Action

NECESSARY COUNCIL ACTION: Approve the closeout change order in the amount of $33,581.80.