File #: 17-0387    Version: 1 Name: Tank Pro Change Orders
Type: Contract Status: Passed
File created: 9/19/2017 In control: City Council
On agenda: 10/10/2017 Final action: 10/10/2017
Title: Approval of Change Orders #1 and #3 with Tank Pro
Sponsors: Catoosa Department
Attachments: 1. Tank Pro Change Orders

Title

Approval of Change Orders #1 and #3 with Tank Pro

 

Body

SUMMARY:

Two change orders have been submitted for approval for the Interchange Park water tank painting project.  Change Order #1 adds 29 calendar days to allow the City to install modifications to their Hwy. 127N pump station so the tank could be taken out of service.

Change Order #3 is a deduct of $6,000, which deletes base bid item 3 that was an allowance for additional miscellaneous improvements.  Change Order #2 was previously approved to add the additional logo.

 

The project is substantially complete.

 

BUDGET ACCOUNT:  450-52140-934-002

 

Recommended Action

NECESSARY COUNCIL ACTION:  Approve Change Orders #1 and #3.