Approval of CDBG 2020 Sewer Rehab Project Change Order
Body
SUMMARY: A change order is attached with a decrease in contract price of $2,425. The adjustment was necessary due to quantities based on the work remaining.
The Director of Engineering recommends the approval of the change order.
BUDGET ACCOUNT:
Recommended Action
NECESSARY COUNCIL ACTION: Approve Change Order in the amount of $2,425.