File #: 21-0361    Version: Name: Airport Layout Plan Amendment
Type: Contract Status: Passed
File created: 10/27/2021 In control: City Council
On agenda: 11/9/2021 Final action: 11/9/2021
Title: Approval of Contract Amendment for Airport Layout Plan (ALP) Engineering Services
Sponsors: Engineering Department, Tim Begley
Attachments: 1. CSV ALP Update - WA 03-19 Amendment No. 1_2021.10.11

Title

Approval of Contract Amendment for Airport Layout Plan (ALP) Engineering Services

 

Body

SUMMARY: The work to be performed by Atkins on the Airport Layout Plan (ALP) has been delayed due to the City postponing the obstruction clearing project. It has been estimated by TDOT and Atkins that the project is one year behind schedule.

Staff requests an extension of the Atkins contract to September 5, 2023.

 

BUDGET ACCOUNT: 110-52500-930-004

 

Recommended Action

NECESSARY COUNCIL ACTION: Approve the contract extension